Thursday, November 11, 2010

Deep Fried Shrimp Calories

winter break

Unfortunately, after several postponements due to bad weather to lift, now the cold is coming and it was necessary to shift the work in early spring, in the second half of February . The processing times are estimated in a month and will cover the blasting of the hull, the recovery of any metal worn, replace the main propeller, the propeller assembly of maneuver, the painting of the hull. It follows that the painting would be done in full December when temperatures are below the allowable range for the various products. then I find myself stuck for a couple of months and I pay a couple of months of occupation of public property for nothing also causing inconvenience to the area granted. But in February even though the temperatures were not enough just best to wait a couple of weeks in March and certainly the climate would be beneficial .
In the meantime I will continue the selection and procurement of various materials needed, which is already difficult in itself.

0 comments:

Post a Comment